Generation Statistics

Print
Press Enter to show all options, press Tab go to next option

General Statistical Information

Metered Rates Per Month Unit No. 1 Unit No. 2 Unit No. 3 Gas Turbine No. 1 Gas Turbine No. 2 Gas Turbine No. 3
Year placed in service 1957 1963 1972 1968 2003 Scheduled for 2004
Rated generation 16.5 mw 22 mw 54 mw 15 mw 40 mw 40 mw
Fuel Nat. gas / No. 6 fuel oil Nat. gas / No. 6 fuel oil Nat. gas / No. 6 fuel oil Nat. gas / No. 2 fuel oil Nat. gas / No. 2 fuel oil Nat. gas / No. 2 fuel oil
Make of turbine Allis/Chalmers Allis/Chalmers General Electric General Electric General Electric General Electric


The C.W. Burdick Station will serve the citizens of Grand Island into the foreseeable future as continued maintenance and upgrades to systems at the plant are planned. New digital control systems that help maximize power production efficiency and monitor plant emissions have been installed for Unit No. 3 and gas turbine No. 1, and control upgrades have been made to Units No. 1 and No. 2.