STREET / LANE CLOSURES WITHIN THE CITY OF GRAND ISLAND


ConeZoneWebApp_wab.png--2018-08-15

          

                                                                  Place mouse over map and click!  hand image-cone zone

**Project Updates (Click here)**

 

BLAINE STREET - COMPLETE CLOSURE- HWY 34 to Schimmer Drive

Status:  Local Traffic Only                Dates: July 29th - Aug 5th 

Work Description: Fiber Install 

Agency: Viaero / Bauer Construction          Ph.#: 

 

FAIDLEY AVENUE  - COMPLETE CLOSURE -Iron Gate Ave. to Diers Ave

Status:  complete closure                  Dates: June 25th -Sept 30, 2020

Work Description: Road Paving Improvement Project 

Agency: GI Public Works Engineering         Ph.#: 308-385-5455 

https://www.grand-island.com/departments/public-works/engineering/2019-planned-projects/old-potash-final-design-north-road-to-webb-road/-fsiteid-1

 

FAIDLEY AVENUE  - COMPLETE CLOSURE -White to Darr

Status:  complete closure                  Dates: July 27th - Aug 10th

Work Description: Concrete Repairs

Agency: GI Public Works Streets Division      Ph.#: 308-385-5322

 

GREENWICH  - COMPLETE CLOSURE - EDDY/FONNER TO PHOENIX 

Status: Complete Closure                                    Dates:  July 30th - September 2020

 Work Description: Water Main Installation 

Agency:  GI Utilities Engineering         Ph.# 308-385-5463  ext 2164

 

KAUFMANN AVENUE -COMPLETE CLOSURE - @ 121 Kaufmann Ave 

Status: Complete Closure                                    Dates:  July 20th - Aug 20th

Work Description:   Paving Improvements

Agency:  GI PW Engineering         Ph.# 308-385-5455

 

LAFAYETTE AVENUE  - COMPLETE CLOSURE - Between Waugh Avenue and College Street  

Status:  Complete Closure                  Dates: June 9th - July 31,  2020

Work Description:  Water Service Project

Agency: Hausmann Construction         Ph.#

 

NORTH ROAD  - COMPLETE CLOSURE - Capital Avenue to Highway 2  

Status:  complete closure of intersection                Dates: April 6th -Dec 2020

Work Description: Road expansion & Roundabout

Agency: GI PW Engineering Division /  Diamond Engineering Company         Ph.#: 308-385-5455

Phase 1 Closure Notice - Spring 2020 FINAL

2020-04-01 North Road - Phase 1 Press Release

 

OLD POTASH HWY - COMPLETE CLOSURE- at North Road

Status:  complete closure   of the intersection                Dates: July 27th - Oct 27th 

Work Description: Road Paving Improvement Project 

Agency: GI Public Works Engineering/ Starostka Group         Ph.#: 308-385-5455 

   

SANITARY SEWER CLEANING - OPEN TO TRAFFIC

Status: Open to Traffic                     Dates: 

Work Description:  Cleaning-  13th to Capital – Custer & Broadwell,  Cleaning 9th to 4th – Congdon to Oak Televising-Ponderosa Subdivision Area

Agency: GI PW Wastewater                                Ph.#: 308-385-5455

 

 

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer