STREET / LANE CLOSURES WITHIN THE CITY OF GRAND ISLAND


ConeZoneWebApp_wab.png--2018-08-15

          

                                                                  Place mouse over map and click!  hand image-cone zone

**Project Updates (Click here)**

 

CONGDON AVENUE- COMPLETE CLOSURE -  5th Street to 6th Street

Status: Complete Closure                  Dates:  November 25- December 2, 2019

Work Description:  Utility Work

Agency:  GI PW Engineering Division              Ph.#:308-385-5455

 

EDDY STREET UNDERPASS- COMPLETE CLOSURE

Status: Complete Closure                  Dates:  December 11, 2019- 8am to 3pm

Work Description:  Structural Assessment

Agency:  GI PW Engineering Division              Ph.#:308-385-5455

 

SANITARY SEWER CLEANING - OPEN TO TRAFFIC

Status: Open to Traffic                     Dates: 

Work Description:  Cleaning-  13th to Capital โ€“ Custer & Broadwell,  Cleaning 9th to 4th โ€“ Congdon to Oak

Televising-Pleasant View to Stuhr Rd. โ€“ Sunset & Fonner Pk. Rd.

Agency: GI PW Wastewater                                Ph.#: 308-385-5455

 

SOUTH FRONT STREET BRIDGE - COMPLETE CLOSURE - Sycamore Street Underpass 

Status: Complete Closure                  Dates:  November 7 - May 15, 2020

Work Description: Sycamore Street Underpass Improvements

Agency:  GI PW Engineering Division              Ph.#: 308-385-5455

  

WILLOW STREET @ 7TH STREET - COMPLETE CLOSURE  

Status: Complete Closure                  Dates:  December 9- December 16, 2019

Work Description: Sanitary sewer main installation

Agency:  GI PW Engineering Division              Ph.#308-385-5455


 

 

 

 

PRAIRIEVIEW STREET - COMPLETE CLOSURE - Husker Hwy. to entrance of Riverbend Apartments

Status: Closed to thru Traffic    Dates: October 16th - November 14th

Work Description:      Private Sewer Line Installation

Agency:  Sampson Construction                 Ph.#: Tom Furse 308-380-3019