This bridge replacement updated the north bridge structure with two (2) box culverts and the south bridge structure with two (2) Arch RCP culvert pipes.  The roadway was also be widened to improve traffic flow in this area.

The Diamond Engineering Co. of Grand Island, Nebraska was awarded the $384,983.95 construction contract on January 13, 2015, with completion July 2016.  Construction work was completed at a total cost of $429,851.12, which included addressing the condition of the asphalt roadway with an upgrade to concrete pavement.  