Sanitary Sewer District No. 538T

Print
Press Enter to show all options, press Tab go to next option

The Wastewater and Public Works Engineering Divisions are planning for a 600-foot sewer extension just east of Engleman Road in between Michigan Avenue and Airport Road.  This sewer extension has the potential to serve four (4) properties and eliminate three (3) septic tanks.

Timeline:

Construction Start: November 2016

Construction End: May 2017

Design, Engineering, and Construction Cost: $42,000